COLUMBIA BASIN PROJECT COMPLETION PROCESS AT A GLANCE

COLUMBIA BASIN PROJECT COMPLETION PROCESS AT A GLANCE

As the Columbia Basin Project (CBP) is the largest Reclamation project in the nation, full development of the authorized 1,029,000 acres was intended to be phased and take multiple decades. Decades since ground breaking on the CBP, it is often asked what it would take to complete the Project. Below, is a high-level overview. Some steps involve multiple years and millions of dollars per step. Construction would require billions of dollars. For comparison, OGWRP construction, alone (excluding bridges), is roughly $2.7 million (with inflation continuing to increase costs).

STEP 1

Authorization Complete

The Columbia Basin Project was authorized by Congress in 1945 f or 1,029,000 acres.

STEP 2

Key Partner Commit to Financial Support

Given its size and scope of work, the CPB requires financial support from multiple

partners such as the Bureau of Reclamation, the St ate of Washington through the

Department of Ecology, Columbia Basin Project Irrigation Districts, and landowners.

STEP 3

Appraisal Study

The Appraisal Study calculates the size and scope of the project along with possible viable

solutions.

STEP 4

Plan of Study

The “Plan of Study” is a guidance document that lays the foundation for doing a

Feasibility Study. The partner s, Congress and the Washington State Legislature, would

fund the study.

STEP 5

Feasibility Study

A detailed evaluation of all aspects of the project—consistent with numerous legal

requirements. This step includes identification of alternatives and viable options to

pursue.

STEP 6

Construction

Full construction of the Projects is difficult to estimate as costs and timeline can only be

determined once all studies are completed, the bene fit/cost ratio is above one, and a

build options is selected.



Stay up to date with Project happenings every month.